J-1042

In Build High

Kerwick EjectX GEN3 19m³ — unit #4

Edit

Work order detail

Customer
Kerwick Earthmoving
Type
New Build
Product
EjectX GEN3 19m³
Shop stage
Fabrication
Lead hand
Wayne Petersen
Vehicle rego
Scheduled
21 May 2026 – 27 June 2026
Quoted value
$214,500
Serial unit
SX-EJ-0311
Build progress55%

Body fabrication underway. On schedule.

Labour logged

24.6 hrs across 5 time entries (from kiosk)

EmployeeTaskClock inClock outHrs
Kane Williams · Apprentice Assembly 06:45 am on the clock
Jake Mooney · Boilermaker Fabrication 06:31 am on the clock
Mitch Farrelly · Fitter (Hydraulics) Hydraulics 07:05 am 03:10 pm 8.08
Dylan Roberts · Boilermaker Fabrication 06:35 am 02:50 pm 8.25
Jake Mooney · Boilermaker Fabrication 06:32 am 02:48 pm 8.27

QA sign-offs

Quality checkpoints & non-conformances

  • Weld inspection — body Pass

    Main body welds inspected, within spec.

    Adam Cossart · 30 May 2026 · 📷 photo attached

Job cost summary

Live cost vs quoted

Labour $68,518
Material $50,140
Sublet $10,300
Paint/Consumable $6,300
Freight $1,700
Total cost$136,958
Quoted value$214,500
Gross margin 36%