J-1042
In Build HighKerwick EjectX GEN3 19m³ — unit #4
Work order detail
- Customer
- Kerwick Earthmoving
- Type
- New Build
- Product
- EjectX GEN3 19m³
- Shop stage
- Fabrication
- Lead hand
- Wayne Petersen
- Vehicle rego
- —
- Scheduled
- 21 May 2026 – 27 June 2026
- Quoted value
- $214,500
- Serial unit
- SX-EJ-0311
Build progress55%
Body fabrication underway. On schedule.
Labour logged
24.6 hrs across 5 time entries (from kiosk)
| Employee | Task | Clock in | Clock out | Hrs |
|---|---|---|---|---|
| Kane Williams · Apprentice | Assembly | 06:45 am | on the clock | — |
| Jake Mooney · Boilermaker | Fabrication | 06:31 am | on the clock | — |
| Mitch Farrelly · Fitter (Hydraulics) | Hydraulics | 07:05 am | 03:10 pm | 8.08 |
| Dylan Roberts · Boilermaker | Fabrication | 06:35 am | 02:50 pm | 8.25 |
| Jake Mooney · Boilermaker | Fabrication | 06:32 am | 02:48 pm | 8.27 |
QA sign-offs
Quality checkpoints & non-conformances
- Weld inspection — body Pass
Main body welds inspected, within spec.
Adam Cossart · 30 May 2026 · 📷 photo attached
Job cost summary
Live cost vs quoted
Labour $68,518
Material $50,140
Sublet $10,300
Paint/Consumable $6,300
Freight $1,700
Total cost$136,958
Quoted value$214,500
Gross margin 36%